CE Construction & Evaluation
Preconstruction, construction phase administration, payment requests, and project closeout.
CE Field Guide
Every topic covered for Construction & Evaluation, written for the exam rather than the textbook. Tap any heading to open it.
01 Claim Procedures (A201 Article 15)
Notice deadlines
| Event | Deadline |
|---|---|
| Initiate claim | 21 days from event or recognition (§15.1.3) |
| Differing site conditions | 14 days from observance (§3.7.4) |
| Architect IDM decision | 30 days from claim |
| Mediation demand | 30 days from IDM decision |
Workflow
- Notice within 21 days
- Submit claim with documentation
- Architect (IDM) issues initial decision in 30 days
- Either party may demand mediation
- Mediation required before binding resolution
- Binding resolution per agreement
Architect (IDM) duties
- Request additional info if needed
- Reject, approve in whole/part, or suggest compromise
- Render written decision with reasoning
- Decision is condition precedent to mediation
Continuing performance
Both parties continue work pending resolution. Disputes don't stop the project.
Mutual waiver of consequential damages (§15.1.7)
Owner waives lost profits, use, rent, business. Contractor waives lost profits on unperformed work and home office overhead. Direct damages still recoverable.
Special situations
- Architect's own claim: cannot be IDM — Owner names alternative
- Emergency (§15.1.5): contractor proceeds, then claims
- Weather (§15.1.6.2): time only if abnormal; no money
02 Schedule of Values & Pay Apps
SOV
Contractor's breakdown of contract sum. Submitted before first pay app per A201 §9.2.
SOV best practices
- Match WBS / construction sequence
- Avoid front-loading (Owner protection)
- Detail line items
- Aggregate to MasterFormat divisions
Pay Application forms
- G702: summary cover (totals, retainage, balance)
- G703: line-item continuation (prior, current, stored, % complete)
Architect's certification (A201 §9.4)
To the best of architect's knowledge, information, and belief:
- Work progressed to indicated point
- Quality consistent with contract docs
- Payment is owed
NOT a representation of exhaustive inspection or approval of means/methods.
Reducing certified amount
Architect may reduce. Must notify BOTH Owner and Contractor of reduction and reasons. No Owner approval needed.
Stored materials (§9.3.2)
Eligible if at approved location, properly insured, title transfers to Owner on payment, with documentation.
Retainage
5-10% typical. Reduced to 5% (or 0%) at Substantial Completion. State law may regulate.
Pay-when-paid vs pay-if-paid
- Pay-when-paid: GC pays sub within reasonable time after Owner pays (timing)
- Pay-if-paid: conditional on Owner payment (risk shift — often unenforceable)
Lien waivers
Conditional (effective on payment) or unconditional (immediately effective). Required with each pay app.
03 Project Closeout Checklist
Substantial Completion (G704)
- Contractor request + punch list
- Architect inspection (may add items)
- G704 signed three-way
- Certificate of Occupancy from AHJ
- Retainage reduced
- 1-yr correction period begins
- LDs cease
- Owner property insurance replaces Builder's Risk
- Beneficial occupancy permitted
Final Completion
- Punch list complete
- Record drawings (as-builts)
- O&M manuals
- Warranties (manufacturer + system)
- Owner training on systems
- Attic stock
- Final cleaning per Division 01
- Test reports
- Final lien waivers (unconditional, all subs)
- G707 Consent of Surety if bonded
- Affidavit of payment of debts (§9.10.2)
- Final certificate
- Final payment + retainage release
Owner-side deliverables
- All permits — final inspections
- Health Dept signoff (food, healthcare)
- Fire Marshal final
- Elevator certification
- LEED/sustainability docs
Common delays
- Outstanding punch list
- Missing test reports
- Sub-contractor lien waivers
- Manufacturer warranties (60-90 day delay common)
- O&M manuals incomplete
04 Submittal Process & Review
Submittal types
| Type | Purpose |
|---|---|
| Product Data | Manufacturer literature |
| Shop Drawings | Contractor fabrication details |
| Samples | Color, texture, material verification |
| Mock-ups | Full-scale assembly verification |
| Certifications | Compliance with standards |
| Test Reports | Performance verification |
| Coordination drawings | Multi-trade overlays |
Review timelines (typical)
| Item | Days |
|---|---|
| Initial review | 7-14 |
| Resubmittal | 5-7 |
| Major package | 14-21 |
Architect's review per A201 §3.12
- Reviews for general conformance with design intent
- Does NOT verify dimensions, quantities, fabrication
- Does NOT approve means/methods
- Does NOT shift responsibility unless contractor specifically informs in writing AND architect approves in writing
Review stamps
| Stamp | Meaning |
|---|---|
| Reviewed — No Exceptions Taken | Approved as submitted |
| Reviewed — Note Markings | Approved with corrections |
| Revise and Resubmit | Major changes; full re-review |
| Rejected | Not conforming; full resubmittal |
Lessons
- Long-lead items: submit early
- Coordination submittals across trades (MEP overlays)
- Approval before fabrication
- Late submittals create scheduling pressure
05 Change Orders, CCDs & ASIs
When to use each
| Doc | When | Signatures |
|---|---|---|
| ASI (G710) | Minor change, NO cost or time | Architect only |
| CO (G701) | Agreed cost AND time | All three parties |
| CCD (G714) | Cost/time NOT agreed; work must proceed | Owner + Architect (not Contractor) |
ASI
- Interpretations, clarifications, minor changes
- Cannot change cost or time
- If cost/time impact → convert to CO or CCD
- Written record of verbal field direction
Change Order (CO)
- All three parties agree on scope, cost, time
- Adjusts Contract Sum and Time
- Backed by SOV adjustment
- Permits may require AHJ resubmittal for major changes
CCD
- Work proceeds before agreement on cost/time
- Owner + Architect sign; Contractor must proceed
- Compensation determined later
- Per A201 §7.3.7 if no agreement:
- Mutual lump sum
- Unit prices
- Cost + agreed fee
- As determined by Architect (subject to claim)
When CCD preferable
- Schedule pressure won't wait
- Scope clear but cost still being analyzed
- Disputed change but Owner needs work performed
Constructive change
Owner/Architect action effectively changes work without formal CO:
- Overly restrictive interpretation
- Acceleration directive
- Defective specs requiring extra work
- Contractor's remedy: claim per §15.1
06 Bonds & Insurance on Projects
Bond types
| Bond | Purpose | Amount |
|---|---|---|
| Bid Bond | Guarantees contractor will execute if awarded | 5-10% of bid |
| Performance Bond | Guarantees performance | 100% of contract |
| Payment Bond | Protects subs/suppliers | 100% of contract |
| Maintenance Bond | Warranty period | Negotiated |
Miller Act
Federal projects > $150,000 require performance AND payment bonds, typically 100% each. State "Little Miller Acts" follow similar pattern.
Private projects
At Owner's discretion. Smaller projects may forgo bonds (saving 1-3% premium) and accept risk.
Insurance — Owner-required typical
| Coverage | Holder | Purpose |
|---|---|---|
| Builder's Risk | Owner | Damage to work during construction |
| CGL | Contractor | Bodily injury, property damage |
| Workers Comp | Contractor | Employee injury |
| Auto | Contractor | Vehicles |
| Umbrella | Contractor | Excess over primary |
| Pollution | Contractor | If hazmat work |
COI (Certificate of Insurance)
- Required BEFORE contractor begins
- Owner named as additional insured (§11.1.4)
- 30-day notice of cancellation
- Verified annually
Waiver of subrogation (§11.3.7)
Owner and Contractor waive rights against each other and their insurers for damages covered by property insurance.
E&O (Architect)
- Claims-made basis
- Owner may require $1M-$5M minimum
- Tail coverage (ERP) essential at retirement/closure
07 Termination & Suspension (A201 Art. 14)
Termination by Contractor (§14.1)
Grounds (work stopped 30+ days, not Contractor fault):
- Court/government order
- Owner failure to pay (after 7-day notice + cure)
- Failure to furnish reasonable evidence of financing
- Repeated suspensions >100% scheduled time
Procedure: 7-day notice. If not cured, may terminate.
Compensation: Work executed + proven loss (materials, equipment) + reasonable OH&P.
Termination by Owner for Cause (§14.2)
Grounds:
- Contractor refuses/fails to supply enough workers or materials
- Fails to pay subs (when Owner pays)
- Persistent disregard of laws/codes
- Material breach
Procedure:
- Architect certifies sufficient cause
- 7-day notice
- Owner may terminate
Compensation:
- Owner finishes work (using contractor's tools/materials)
- Contractor paid only if costs to finish < unpaid balance
- If costs exceed, Contractor + Surety pay difference
Suspension by Owner for Convenience (§14.3)
- Suspend in whole or part
- Cost and schedule adjustment to Contractor
- No profit on suspended work
- Cannot substitute for termination for cause
Termination by Owner for Convenience (§14.4)
- Owner may terminate at any time
- Compensation: work executed + termination costs + reasonable OH&P on unexecuted work (if specified)
Architect's role
- Certifies sufficient cause for §14.2 termination
- Document everything precisely
- Continue impartial role
- Get legal counsel — termination is high-stakes
08 AIA G-Series Quick Reference
The G-series — administrative forms used during construction
Most important to memorize
| Form | Title | When Used |
|---|---|---|
| G701 | Change Order | Formal change to contract sum/time |
| G702 | Application & Certificate for Payment | Each pay app |
| G703 | Continuation Sheet | Goes with G702; line items |
| G704 | Certificate of Substantial Completion | At substantial completion |
| G707 | Consent of Surety to Final Payment | Final pay (when bonded) |
| G710 | Architect's Supplemental Instructions (ASI) | Minor change, no $/time |
| G711 | Architect's Field Report | Document site visits |
| G714 | Construction Change Directive (CCD) | Owner-directed change, $ disputed |
| G715 | Supplemental Attachment for ACORD 25 | Additional insured certification |
| G716 | Request for Information (RFI) | Standardized RFI form |
Owner-Architect amendment series
| Form | Title |
|---|---|
| G801 | Notice of Amendment to Professional Services Agreement |
| G802 | Amendment to Professional Services Agreement |
| G803 | Amendment to Consultant Services Agreement |
| G806 | Project Parameters Worksheet |
| G808 | Project Directory |
Decision/notice
| Form | Title |
|---|---|
| G706 | Contractor's Affidavit of Payment of Debts |
| G706A | Contractor's Affidavit of Release of Liens |
| G731 | Architect's Decision on Claim |
09 AIA B-Series Owner-Architect
B-series — Owner-Architect agreements
Main agreements
| Form | Purpose |
|---|---|
| B101 | Standard form — design-bid-build, most common |
| B102 | Standard form WITHOUT scope of services (use with B201/B203/B205) |
| B103 | For large or complex projects (modified terms) |
| B104 | Limited scope, smaller projects |
| B105 | Residential or small commercial |
| B106 | Pro bono services |
| B132 | CMa edition (CM as Adviser) |
| B133 | CMc edition (CM as Constructor) |
| B143 | Design-Builder/Architect agreement |
| B144 | Design-Build subagreement |
Scope-of-services modules (paired with B102)
| Form | Service |
|---|---|
| B201 | Design and Construction Contract Administration |
| B203 | Site Evaluation |
| B204 | Value Analysis |
| B205 | Historic Preservation |
| B206 | Security Evaluation |
| B207 | On-site Project Representation |
| B209 | Construction CA (separated from design) |
| B210 | Facility Support |
| B211 | Commissioning |
| B214 | LEED Certification |
10 AIA A-Series Owner-Contractor
A-series — Owner-Contractor agreements
Main agreements
| Form | Use |
|---|---|
| A101 | Stipulated Sum, design-bid-build |
| A102 | Cost-Plus + GMP, design-bid-build |
| A103 | Cost-Plus, no GMP |
| A104 | Abbreviated form, small projects |
| A105 | Stipulated sum, no architect / very small |
| A107 | Cost-Plus, no GMP, abbreviated |
| A132 | CMa edition (CM Adviser) |
| A133 | CMc edition, GMP |
| A134 | CMc edition, no GMP |
| A141 | Design-Builder/Owner agreement |
| A142 | Design-Build subagreement |
| A195 | IPD - Sustainable Projects |
General conditions
| Form | Use |
|---|---|
| A201 | General Conditions — referenced by most A and B contracts |
| A232 | CM-as-Adviser General Conditions |
| A295 | IPD General Conditions |
Bidding / Procurement
| Form | Use |
|---|---|
| A305 | Contractor's Qualification Statement |
| A310 | Bid Bond |
| A311 | Performance Bond / Payment Bond |
| A312 | Performance Bond / Payment Bond (updated) |
| A701 | Instructions to Bidders |
11 CA Decision Tree
What document do I use?
Is there a change to the work?
├── Yes
│ ├── No cost or time impact?
│ │ └── ASI (G710) — minor change
│ ├── Owner directs immediately, cost disputed?
│ │ └── CCD (G714) — contractor proceeds, claim later
│ └── Agreed cost and time?
│ └── CO (G701) — signed by all three parties
└── No change
├── Need clarification?
│ └── RFI (G716 or similar)
├── Substitution request?
│ └── Substitution Request form (Division 01)
├── Submittal review?
│ └── Submittal log + stamp
└── Schedule update?
└── Updated schedule per spec section 01 32 00
Communication tools
- Field Report (G711) — document site visit
- RFI — questions and clarifications
- Submittals — shop drawings, samples, mockups
- Meeting Minutes — record decisions
- Issue Log — track open items
When in doubt
- Document everything in writing
- Use AIA forms when available
- Check Owner-Architect agreement for additional services trigger
- Notify all affected parties
12 Substantial Completion Procedure
Per A201 §9.8
Step 1 — Contractor notifies
Contractor's written notice that work is sufficiently complete + submitted punch list
Step 2 — Architect inspects
Architect determines if substantial completion achieved
- Yes: proceed to Step 3
- No: notify contractor of incomplete items; repeat when ready
Step 3 — Architect prepares G704
Certificate of Substantial Completion containing:
- Date of substantial completion
- Punch list with time to complete
- Responsibilities (security, maintenance, utilities, insurance, damage)
- Warranty start date (unless otherwise specified)
Step 4 — All three sign
Owner, Architect, and Contractor sign G704
What triggers at Substantial Completion
- ✅ Owner can occupy for intended use
- ✅ 1-year correction period begins
- ✅ Warranties begin (unless otherwise specified)
- ✅ Retainage typically reduced (e.g., 10% → 5%)
- ✅ Risk of loss transfers to Owner
- ✅ Liquidated damages STOP (if any)
- ✅ Final completion date target set
What doesn't change
- Contractor obligations to complete punch list
- Warranties (separate from 1-year correction period)
- Statute of repose timing (varies by state)
- Final payment requirements
Partial Substantial Completion (§9.9)
- Owner may occupy portion before whole project complete
- Requires written agreement: Owner + Contractor + Architect
- Identifies occupied portion clearly
- Documents responsibilities for occupied portion
- Insurance adjustments must be coordinated
13 Insurance Coverages on a Project
Who carries what
Owner typically carries (per A201 §11.2)
- Property insurance (Builder's Risk during construction)
- All-risk / special perils form
- Covers site materials, equipment, work in progress
- Owner adds Contractor + Subs as additional insureds
- Continues until substantial completion
- General liability (premises)
- Loss of use insurance (optional)
Contractor typically carries (§11.1)
- Commercial General Liability (CGL)
- Bodily injury / property damage
- Per occurrence + aggregate limits
- Includes products & completed operations
- Names Owner, Architect, Consultants as additional insureds
- Automobile liability
- Workers' Compensation (state-required)
- Employer's Liability
- Other per supplementary conditions
Architect carries
- Professional Liability (E&O)
- Claims-made basis
- Tail coverage for closure/transition
- Tied to scope of services
Subcontractors carry
- Required by contractor — flow-down provisions
- Typically include CGL, Auto, WC at minimum
Builder's Risk vs. Property
- Builder's Risk: During construction; covers work in progress
- Property: After substantial completion; Owner's normal property coverage
- Transition managed at substantial completion
Waivers of Subrogation (§11.3.7)
- All parties waive rights against each other for losses covered by insurance
- Prevents insurance disputes from undermining the project team
- Critical clause in A201
14 Bidding Procedures
Bid documents (in Project Manual but NOT contract)
- Advertisement / Invitation to Bid
- Instructions to Bidders (AIA A701)
- Supplementary Instructions
- Bid forms
- Bid security info
- Performance & Payment bond forms
Bid bonds
- Form: Surety guarantee bidder will honor bid
- Typical amount: 5-10% of bid
- Forfeited if: Low bidder refuses award
Public bid opening process
- Architect conducts opening with Owner
- Bids read aloud
- Bid log documents amounts, alternates, addenda
- NO announcement of "apparent low bidder"
- Evaluation: 7-10 days typical
- Award notice to ALL bidders
If all bids exceed budget (Owner's 4 options)
- Rebid (architect assists at no fee)
- Increase budget
- Revise scope (architect redesigns at no fee)
- Abandon project
15 Bonds & Insurance
Three primary construction bonds
| Bond | Amount | Purpose |
|---|---|---|
| Bid bond | 5-10% of bid | Bidder honors bid |
| Performance | 100% of contract | Completion of work |
| Payment | 100% of contract | Subs/suppliers paid |
Miller Act (federal)
- Performance + Payment bonds required
- All federal construction over $150,000
- States: "Little Miller Acts" for state work
Builder's Risk insurance
- Covers property under construction (fire, theft, vandalism)
- Typically Owner-provided per A201 §11
- Special perils form preferred
- Covers materials on/off site (with conditions)
Contractor's required insurance (A201 §11.1)
- Commercial General Liability
- Automobile Liability
- Workers' Compensation
- Employer's Liability
- Other types per supplementary conditions
16 Claims & Dispute Resolution
Time limits (A201)
- 21 days to file a claim from event/recognition
- Initial Decision Maker (IDM) decision: 10 days
- Mediation: condition precedent to binding resolution
Order of resolution
- Claim filed with IDM (default: architect)
- IDM decision within 10 days
- Mediation (mandatory before binding)
- Binding resolution (arbitration or litigation, per agreement)
Common claim types
- Time extensions: delays beyond contractor control
- Cost adjustments: changed conditions, owner-caused delays
- Concealed/unknown physical conditions (§3.7.4)
- Differing site conditions: subsurface, hazardous materials
Force majeure (§8.3.1)
Excuses time only (not cost) for:
- Acts of God, fire, weather
- Labor disputes, embargoes
- Owner delays
- 21-day notice required
17 Schedule Compression
Methods to recover schedule
- Crashing — adding resources/overtime. More $.
- Fast-tracking — overlapping activities. More risk.
- Re-sequencing — change logic where possible
- Scope reduction — Owner agreement
- Adding shifts — multiple workforce shifts
Cost slope (for choosing crash candidates)
Cost Slope = (Crash Cost − Normal Cost) ÷ (Normal Days − Crash Days)
Lower slope = cheaper to crash → crash these first.
Critical path & float
- Total float = time activity can slip without delaying project
- Free float = time activity can slip without delaying its successors
- Critical path activities have zero total float
- Float can go negative (project is late)
Liquidated damages
- Daily $ amount for unexcused delay past substantial completion
- Must be reasonable estimate of damages (not a penalty)
- Stops at substantial completion (not final)
18 Termination
Owner termination of Contractor
For cause (§14.2)
- Repeated refusal/failure to supply enough workers/materials
- Failure to pay subcontractors
- Repeated disregard of laws/orders
- Other substantial breach
Process:
- 7-day written notice
- Architect must certify cause
- Owner may take possession of work
- Withhold further payment until completion
- Contractor reimburses Owner for excess costs
For convenience (§14.4)
- No cause needed
- Contractor entitled to:
- Payment for work executed
- Reasonable termination costs
- Reasonable overhead and profit on unexecuted work (if specified)
Contractor termination of Owner (§14.1)
Permitted if:
- Owner failure to pay 30 days after Architect's certificate
- Work suspended >30 consecutive days
- Owner failure of substantial obligation
- 7-day written notice required
19 Delivery Methods
Quick reference
| Method | Architect's Master |
|---|---|
| DBB | Owner (agent) |
| CMa | Owner; CM advises only |
| CMc | Owner; CM holds GMP |
| DB | Design-Builder (contractor) |
| IPD | Multi-party / shared risk |
Selection Methods
- QBS — qualifications first, price negotiated after
- Best Value — weighted score of quals + price
- Low Bid — sealed bids, lowest responsive bidder wins
20 Submittals
Four types
- Shop drawings — contractor/fab-prepared
- Product data — manufacturer cut sheets, specs
- Samples — physical examples
- Mock-ups — full-size site assemblies
Review stamps
- No Exceptions / Approved — proceed
- Make Corrections Noted — proceed with notes
- Revise & Resubmit — do NOT proceed
- Rejected — replace
21 Changes in the Work
Decision logic
| Instrument | Signed By | Cost/Time? |
|---|---|---|
| CO | O + A + C | Agreed |
| CCD | O + A | Not agreed |
| Minor Change | A only | No impact |
| ASI | A only | Clarifies docs |
Flow
- Agreement on cost + time → CO
- Must proceed, disputed terms → CCD
- No cost/time/design impact → Minor Change
- Clarifying docs → ASI (G710)
- Genuine ambiguity → RFI
22 Pay Applications
Documents
- G702 — Application & Certificate for Payment (cover)
- G703 — Continuation Sheet (SOV line items)
- SOV — Schedule of Values, set before first pay app
Retainage
Typical 5–10% withheld. Released at substantial completion (less punch list amounts); final balance at final completion.
Grounds to WITHHOLD (§9.5.1)
- Defective work not remedied
- Third-party claims filed or likely
- Failure to pay subs/materials
- Damage to Owner or separate contractor
- Schedule slippage threatening LDs
- Persistent failure to follow docs
23 Non-Conforming Work
Architect's options
- Reject + require correction (§12.2)
- Require testing (cost on contractor if non-conforming)
- Accept with deduction via CO (needs Owner consent)
- Recommend Owner stop work
Correction period vs. warranty
- 1-yr correction (§12.2.2) — contractual, NOT a warranty
- Warranties — separate, often longer, per specs & mfrs
Uncovering work (§12.1)
- Architect requested it, contractor covered anyway → contractor pays
- Architect didn't request; conforms → Owner pays
- Architect didn't request; non-conforming → contractor pays
24 Closeout
Substantial completion
- Owner can occupy / use for intended purpose
- Certificate: G704
- Punch list created
- Warranties typically begin
- Retainage reduced (less punch list)
Final completion
- All punch list resolved
- All closeout docs submitted
- Final certificate of payment issued
- Remaining retainage released
Closeout docs
- Record drawings (as-builts)
- O&M manuals
- Warranties
- Lien waivers + Consent of Surety
- Certificate of Occupancy
- Spare parts / attic stock
- Commissioning reports
25 Architect's Role
What architect DOES
- Visits site at intervals appropriate to stage
- Endeavors to guard Owner against defects
- Reviews submittals for general conformance with design intent
- Acts as initial interpreter, endeavors to be impartial
- Has authority to reject non-conforming work
- Certifies pay applications
What architect DOES NOT
- Control means, methods, sequences, procedures
- Supervise the work / continuous on-site
- Bear responsibility for contractor safety
- Guarantee the contractor's performance
- Issue stop-work orders (Owner only)
Study CE the way it's tested