ARE 5.0 Division

PPD Project Planning & Design

Environmental conditions, building design, structural systems, building envelope, and systems integration.

140Flashcards
25Field Guide topics
110Practice questions
3Mock exams

PPD Field Guide

Every topic covered for Project Planning & Design, written for the exam rather than the textbook. Tap any heading to open it.

01 Energy & Envelope Standards

Key standards

Standard Topic
IECC International Energy Conservation Code
ASHRAE 90.1 Energy Standard for Buildings Except Low-Rise Residential
ASHRAE 62.1 Ventilation for Acceptable IAQ
ASHRAE 55 Thermal Comfort

Climate zones (IECC)

Zone Climate Typical
1 Very Hot Miami, Honolulu
2 Hot Houston, Phoenix
3 Warm LA, Atlanta
4 Mixed DC, NYC, St. Louis
5 Cool Chicago, Boston
6 Cold Minneapolis
7 Very Cold Duluth, Anchorage
8 Subarctic Northern Alaska

Sub-classifications: A (moist), B (dry), C (marine)

Envelope U-factor prescriptive (commercial Zone 5)

Component U-factor
Walls (steel framed) 0.064
Walls (mass) 0.080
Roof above deck 0.039 (R-30 ci)
Floor over outside air 0.038
Glazing 0.36-0.42
Slab edge F-0.54

Glazing performance

Metric Description
U-factor Heat transmission (lower better)
SHGC Solar Heat Gain Coefficient (0-1)
VT Visible Transmittance (0-1)
LSG Light-to-Solar-Gain (VT ÷ SHGC)

SHGC targets:

  • Cold climate: 0.40-0.55 (capture winter solar)
  • Hot climate: 0.25 or lower (block sun)
  • Mixed: 0.25-0.40

Vapor retarder placement

Climate Placement
Cold (Zone 5+) Interior (warm side)
Hot/Humid (Zone 1-3A) Exterior (warm humid side)
Mixed (Zone 4) Vapor-open assembly or smart retarder

Air barrier

Required by IECC and ASHRAE 90.1. Continuous around envelope. Testing:

  • Blower door (residential)
  • Whole-building pressurization (commercial)

Air leakage often bigger moisture issue than vapor diffusion.

Continuous Insulation (ci)

Required by IECC in many zones. Outboard of studs eliminates thermal bridging (which reduces effective R-value 30-50%).

02 Structural Rules of Thumb

Beam depth estimates

System Span/Depth Ratio
Steel W-beam L/20 (L/15-L/24 range)
Steel joist (K-series) L/20
Steel joist (LH long-span) L/20
Wood joist L/15-L/20
Glulam beam L/16-L/20
Concrete one-way slab L/24 (SS), L/28 (cont)
Concrete two-way slab L/30
Post-tensioned slab L/40+
Concrete beam L/12-L/16

Column sizing

Tributary area × load = axial demand
Office typical: ~70 psf total (DL + LL)

  • W-shape: select from tables based on axial + slenderness
  • HSS: efficient compression, cleaner appearance
  • Concrete: reinforced or post-tensioned

Foundation systems

System When
Spread footing Soil bearing adequate (≥2,000 psf), no expansion, no high water table
Strip footing Continuous load (load-bearing walls)
Mat foundation Weak/uniform soils, high water table
Drilled shaft / pier Transfer load to deeper layer
Driven pile Deep competent layer, urban (timber/steel H/concrete)
Helical screw Light loads, retrofit, low vibration

Frost line depth (foundations below)

Region Depth
S Florida 0"
Mid-Atlantic 24-30"
Midwest 36-42"
N New England 48-54"
N Minnesota 60"

Soil bearing capacity (allowable)

Soil Bearing
Bedrock 8,000-25,000+ psf
Dense sand 3,000-5,000 psf
Stiff clay 2,000-4,000 psf
Loose sand 1,500-3,000 psf
Soft clay <1,500 psf (deep foundations)

Loads (typical)

Load Type psf
Office LL 50
Office partitions 15
Retail LL 75-100
Residential LL 40
Assembly fixed 60
Assembly movable 100
Library reading 60
Library stacks 150
Parking 40 (passenger), 80 (trucks)
Roof 20 (snow varies by location)

Lateral systems

System R Performance
Special steel moment 8 High ductility
Special steel braced 6 High strength
Special concrete moment 8 High ductility
Special shear wall 6 High strength
Ordinary moment 3 Limited ductility

Higher R = lower seismic force = more deformation expected.

Seismic base shear

V ≈ Cs × W

  • W = building weight
  • Cs depends on site class, spectral acceleration, period, R, Ie
  • Heavier buildings get more seismic force
03 HVAC Systems — Selection by Building Type

System types

System Application Pros Cons
VAV (Variable Air Volume) Office, larger commercial Energy efficient, zoning Complex controls
CAV (Constant Air Volume) Smaller buildings, critical spaces Simpler Less efficient
VRF/VRV Mid-size commercial, residential Heat recovery between zones Higher upfront
Chilled Beam Office, lab Efficient, quiet, low ductwork Humidity control critical
Radiant (floor/ceiling) Residential, civic Comfort, low air movement Slower response
Packaged RTU Big box, warehouse, low-rise Simple, low cost Less control
Geothermal HP Mid-size with balanced loads Very efficient, long life High upfront, drilling

Cooling tonnage rules of thumb

Building SF/ton
Restaurant 100-200
Healthcare 250-300
Retail 300-400
Office (efficient) 400-500
School 300-500
Library 400-600
Warehouse 1,000+

Air change rates (ASHRAE 62.1)

Space OA rate
Office 5 cfm/person + 0.06 cfm/SF
Conference 5 cfm/person + 0.06 cfm/SF
Classroom 10 cfm/person + 0.12 cfm/SF
Patient room 25 cfm/person
Operating room 20+ ACH
Lab 6-10+ ACH (negative pressure)
Restroom 50 cfm/WC or 25 cfm/SF exhaust

Energy recovery (ERV/HRV)

  • ERV: sensible + latent (humidity) transfer
  • HRV: sensible only
  • 50-75% effectiveness typical
  • Required by ASHRAE 90.1 above certain airflow thresholds

Economizer

  • Free cooling using outside air when conditions favorable
  • ASHRAE 90.1 requires above certain capacity
  • Climate-dependent value (huge in temperate zones)

DCV (Demand-Controlled Ventilation)

CO2-based airflow modulation. Energy savings in spaces with variable occupancy (conference rooms, classrooms, assembly).

04 Electrical System Sizing & Distribution

Service sizing (residential)

Type Service
Small residence 100 A
Typical new home 200 A
Large + EV + HVAC 200-400 A

Commercial service

Sized per NEC Article 220 load calc:

  • Lighting (per LPD × area + factors)
  • Receptacles (180 VA per outlet, but factors apply)
  • HVAC (largest motor + 100% other motors)
  • Specific loads (kitchens, elevators, etc.)
  • Demand factors per use type

Voltage systems

System Use
120/240 V single phase Residential, small commercial
120/208 V 3-phase Light commercial
277/480 V 3-phase Commercial (lighting, motors)
480/277 V Large commercial industrial
2400/4160 V Industrial, large institutional

Branch circuit standards

  • 15 A: lighting, general outlets
  • 20 A: kitchens, bathrooms (GFCI required), commercial general
  • 30 A: dryers, water heaters
  • 50 A: ranges, EV chargers

Panel locations

  • Accessible (NEC 240.24)
  • 30" wide × 36" deep clearance (working space)
  • Not in bathrooms, closets with combustibles
  • Headroom 6'-6" minimum

Conduit & wire

  • EMT (electrical metallic tubing): light commercial, exposed
  • RMC/IMC (rigid): hazardous, industrial, exterior
  • PVC: underground, wet locations
  • AC/MC cable (armored): commercial, accessible

Grounding & bonding

Critical for safety. NEC Article 250:

  • Service ground rod or building grounding electrode system
  • Equipment grounding conductor through all branch circuits
  • Bonding jumpers at metallic systems

Emergency power

Type Use
Emergency (NEC 700) Life safety: egress, exit signs, alarms — 10-sec transfer
Legally required standby (NEC 701) Heating/refrigeration, communications — 60-sec
Optional standby (NEC 702) Convenience — variable
05 Plumbing System Fundamentals

Water supply sizing

  • Water Supply Fixture Units (WSFU) per IPC table
  • Pressure: 40-80 psi typical from utility (50-60 ideal)
  • Friction loss + elevation + fixture demand
  • Main 3/4"-1" residential typical; commercial sized per WSFU

Drainage Fixture Units (DFU)

Fixture DFU
WC (flush valve) 6-8
WC (tank) 3-4
Lavatory 1
Shower 2
Tub 2
Kitchen sink 2
Floor drain 2
Dishwasher 2

Pipe sizing — drainage

Pipe size Max DFU (horizontal branch)
1-1/2" 3
2" 6
3" 20
4" 160
6" 620

Venting

  • Every fixture trap requires vent
  • Vent termination 6" above flood level rim of fixtures (general)
  • Vent extension 12" above roof in cold climate (frost closure)
  • Combined drain/vent allowed for some fixtures (wet venting)

Hot water

  • Storage tank vs tankless vs heat pump
  • Recirculation for distant fixtures (energy code may require if length exceeds threshold)
  • 120°F at fixtures (scald prevention); 140°F at tank (Legionella prevention)
  • Mixing valves for showers/lavatories

Fixture counts (IBC/IPC)

Group B (office, sprinklered):

  • Lavatories: 1 per 40 occupants
  • WCs: 1 per 25 for first 50, then 1 per 50
  • Drinking fountains: 1 per 100 occupants (or bottle filler)

Group A-2 (restaurant):

  • Higher density requirements
  • Per occupant load × 1/75 (M+F separate)

Code references

  • IPC (International Plumbing Code) — most jurisdictions
  • UPC (Uniform Plumbing Code) — Western states
  • NFPA 99 healthcare-specific
  • ANSI/ASHRAE 188 (Legionellosis prevention)
06 Roofing Systems Comparison

Low-slope (commercial) systems

System Description Life Notes
TPO Thermoplastic Polyolefin 20-30 yr White, reflective, common
PVC Polyvinyl Chloride 20-30 yr More chemical-resistant
EPDM Synthetic rubber 30+ yr Black or white, durable
Modified Bitumen Asphalt + polymer 15-25 yr Torch or self-adhered
BUR (Built-up) Multiple ply + asphalt 20-30 yr Heavy, well-proven
Liquid-applied Fluid membrane 15-25 yr Complex shapes
Metal (standing seam) Metal panels 40-50 yr Higher initial, long life

Slopes

  • Low-slope: ≤2:12 (typically 1/4" per foot minimum drainage)
  • Steep-slope: >2:12 (shingles, tiles, metal)

Drainage requirements

  • Primary: handles design storm (often 100-year)
  • Overflow: backup; scuppers or secondary drains 2"+ above primary
  • Critical: ponding water can collapse roof

Insulation placement

  • Above deck (most common low-slope): no thermal bridging, cool roof
  • Below deck (attic): cheaper but thermal bridging through joists
  • Mass timber/exposed structure: insulation above deck

Cool roof (LEED, energy codes)

  • SRI ≥29 (low-sloped) or ≥39 (steep) per LEED v4.1
  • White TPO/PVC easily exceeds (SRI 80+)
  • Reduces heat island, building cooling load

Green roof

  • Extensive: 3-6" media, lightweight (10-35 psf wet), sedums
  • Intensive: 8"+ media, heavy (80-150+ psf wet), rooftop gardens
  • Stormwater retention, biodiversity, insulation, longer membrane life

Photovoltaic

  • BIPV (Building Integrated PV): replaces membrane
  • Rack-mounted: above existing roof
  • Adds load (5-8 psf typical)
  • Structural review required

Flashing detailing

  • Step flashing at vertical surfaces
  • Counterflashing over base flashing
  • Pipe boots (pre-fabricated)
  • Drains: 2-piece with clamping ring
  • Coordination with parapet, walls, equipment
07 Daylighting & Glazing Design

Daylight Factor (DF)

Ratio of interior to exterior illuminance under overcast sky:

  • 2% adequate for general office task
  • 5%+ preferred
  • Toplighting (skylights, monitors) gives more uniform DF
  • Sidelighting usable to ~2× ceiling height from window

Glazing performance metrics

Metric Description Target
U-factor Heat transmission Lower = better insulator
SHGC Solar Heat Gain Coefficient (0-1) Climate-dependent
VT Visible Transmittance (0-1) Higher = more daylight
LSG Light-to-Solar Gain (VT ÷ SHGC) Higher = more daylight per heat

SHGC targets by climate

Climate SHGC
Cold (Zone 5+) 0.40-0.55 (capture winter solar)
Mixed (Zone 4) 0.25-0.40
Hot (Zone 1-3) 0.25 or lower

Low-e coatings

  • Hard coat (pyrolytic): durable, can face outside
  • Soft coat (sputtered): better performance, must be in insulating air space
  • Spectrally selective: high VT, low SHGC

Shading strategies

  • Overhangs (south): depth ≈ 50% of glazing height (temperate)
  • Vertical fins (east/west): low-angle sun harder to control
  • Exterior shades (blinds, screens): most effective at blocking solar before glass
  • Interior shades: less effective (heat already inside) but glare control

Light shelves

  • Horizontal element on interior of south windows
  • Bounces light deeper into space (off ceiling)
  • Reduces glare near window, increases daylight at back
  • Combined with proper ceiling reflectance (>70%)

Daylight harvesting controls

  • Photosensors dim electric lights based on daylight available
  • Required by ASHRAE 90.1 in daylit zones
  • 25-50% lighting energy savings

Glare control

  • Discomfort glare: subjective, distracting
  • Disability glare: prevents seeing task
  • Mitigation: blinds, fritted/screened glass, exterior shading, indirect lighting

Hurricane glazing (HVHZ zones)

  • ASTM E1996 + E1886 test standards
  • Laminated glass + anchored frame as system
  • Required: Miami-Dade, Broward, coastal FL
  • Alternative: shutters per code
08 Acoustic Design

Sound metrics

Metric Description
STC Sound Transmission Class (airborne — walls, floors, doors)
IIC Impact Insulation Class (impact — floor/ceiling)
NRC Noise Reduction Coefficient (absorption — 0-1)
NIC Noise Isolation Class (field-measured)
dBA Decibels A-weighted (sound level)

STC ratings (typical)

Assembly STC
Hollow core door 20-25
Single layer GWB stud wall 33-35
Double layer GWB stud wall 45-50
Office demising wall 45-50
Apartment unit walls (code) 50+
Hotel between rooms 50-55
Theater walls 60+
Recording studio 70+

IIC ratings (floor-ceiling)

Assembly IIC
Slab only 25-30
Carpet + pad on slab 50-60
Tile/wood on slab 30-40
Code apartments 50+

Detail matters

  • Penetrations: outlets back-to-back, plumbing, ducts destroy STC
  • Doors: STC of weakest element governs (door usually ≪ wall)
  • Ceiling continuation: walls to deck (not just to ceiling) for true STC
  • Flanking: sound around or through adjacent assemblies

Absorption (interior acoustics)

  • NRC 0.0-1.0 (1.0 = total absorption)
  • Acoustic ceiling tiles: NRC 0.65-0.95
  • Carpet: NRC 0.20-0.55
  • Hard surfaces: NRC 0.00-0.05

Reverberation Time (RT)

Time for sound to decay 60 dB:

  • Speech intelligibility: 0.5-1.0 sec
  • Music concert hall: 1.5-2.0 sec
  • Cathedral: 4-6+ sec
  • Calculated: RT60 = 0.049 × V ÷ (Σ Sα) [V volume, S surface area, α absorption]

Background noise (NC/RC)

  • Private office: NC 30-35
  • Open office: NC 35-40
  • Library reading: NC 30-35
  • Hospital exam: NC 30-35
  • Classroom: NC 30 (ANSI standard)
  • Auditorium: NC 20-25

ANSI standard S12.60 (classrooms)

  • Background noise ≤35 dBA
  • RT ≤0.6 sec (small) or 0.7 sec (large)
  • Critical for speech intelligibility, especially for hearing-impaired
09 Fire Protection Systems

Sprinkler standards

Standard Application
NFPA 13 Full system; unlocks IBC trade-offs
NFPA 13R Residential up to 4 stories
NFPA 13D 1-2 family dwellings (life safety only)

NFPA 13 IBC trade-offs unlocked

  • Area increases (200% under §506.3)
  • Height increases (+20 ft + 1 story per §504)
  • Travel distance increased (e.g., B 200 → 300 ft)
  • Reduced fire ratings (e.g., 1-hr corridors → 0-hr in many cases)
  • Dead-end corridors increased (B 20 → 50 ft)

Sprinkler hazard classifications

Class Density (gpm/sf) Examples
Light Hazard 0.10 Office, school, hospital, hotel
Ordinary 1 0.15 Restaurant, retail
Ordinary 2 0.20 Print shop, warehouse
Extra Hazard 0.30-0.60 Aerosol storage, plastics

Sprinkler systems

  • Wet pipe (most common): water in pipes ready to flow
  • Dry pipe (freeze risk): air in pipes, water at valve
  • Pre-action (sensitive areas): requires two events to activate
  • Deluge (high hazard): all heads open, manual trigger

Standpipes (NFPA 14)

Class Hose Use
Class I 2-1/2" Fire department only
Class II 1-1/2" Trained occupants
Class III Both Both populations

Required for buildings above 30 ft above lowest fire dept access (varies).

Fire alarm (NFPA 72)

  • Initiating devices: manual pull, smoke detector, heat detector, water flow
  • Notification appliances: horn/strobe, voice evacuation, visual for hearing-impaired
  • Control panel: monitors, supervises, signals
  • Power: AC + 24-hr battery backup
  • Voice evacuation required: Group A 1000+ occupants, high-rises, certain occupancies

Fire-rated assemblies

  • Walls: per UL design (e.g., UL U419 for 1-hr GWB)
  • Doors: per NFPA 80 (e.g., 90-min in 2-hr wall)
  • Penetrations: firestopping per ASTM E814/UL 1479
  • Glazing: fire-protective vs fire-resistive (different criteria)

Smoke control

  • Smoke barriers: contain smoke (I-2 every 22,500 SF max)
  • Smoke partitions: less stringent than barriers
  • Pressurization: stair pressurization in high-rise
  • Smoke exhaust: atria, malls
10 Vertical Transportation

Elevator types

Type Application Speed Travel
Hydraulic Low-rise (≤5 stories) ≤150 fpm ≤60 ft
MRL (Machine-Room-Less) Mid-rise 150-500 fpm ≤200 ft
Traction (geared) Mid-rise 100-500 fpm Up to 250 ft
Traction (gearless) High-rise 500-1,800 fpm Unlimited
Destination dispatch Tall buildings Variable Optimized

Capacity & sizing

Use Capacity Notes
Office 2,500-4,000 lb 16-25 person
Residential 2,500-3,500 lb 16-21 person
Service 4,500-5,000 lb Carts, larger pieces
Hospital 5,000-6,000 lb Stretcher/gurney
Freight Per loading Heavy equipment

Elevator banking (population analysis)

Handling Capacity (HC) = passengers carried in 5 min ÷ population × 100

  • Office target: 12-15%
  • Hospital target: 8-10%
  • Residential target: 5-8%

Average Interval (AI) = waiting time between cars

  • Office: 25-35 seconds acceptable
  • Premium: <25 seconds

Shaft & machine room

  • MRL: no machine room, hoist machine in shaft
  • Traditional: machine room above (overhead) or below (basement)
  • Shaft sized per car capacity + clearances
  • Pit depth per code (5-10+ ft, varies)
  • Overhead clearance above top floor

Code compliance

  • ASME A17.1: Safety Code for Elevators and Escalators
  • ADA: accessible: 80" car min, controls 15-48" reach, audible signals
  • Fire service operation: Phase I (recall), Phase II (firefighter operation)
  • Emergency power: required for high-rise (one car at a time)

Escalators

  • 24-30" tread width (typical commercial)
  • 30° incline (typical)
  • 100-120 fpm typical
  • Sized for peak flow
  • Two-direction common; one-direction in lower-volume

Lifts & dumbwaiters

  • Wheelchair lifts: ADA accessible vertical transport (short distances)
  • Platform lifts: industrial/freight
  • Dumbwaiters: materials only, not occupied
  • Some loophole avoidance in code (compliance check required)
11 Foundations — Systems & Selection

Shallow foundations

Type When
Spread footing Concentrated load, adequate bearing
Strip footing Continuous load (bearing wall)
Combined footing Adjacent columns close to property line
Mat (raft) Weak/uniform soils, high water table

Deep foundations

Type When
Driven pile (timber) Light loads, accessible
Driven pile (steel H) Heavy loads, urban (noise/vibration issues)
Driven pile (precast concrete) Medium-heavy loads
Drilled shaft / caisson Heavy loads, less vibration
CFA (Continuous Flight Auger) Loose to medium soils
Helical screw Light loads, retrofit, low vibration
Micropile Restricted access, retrofit, restoration

Pile capacity

  • End bearing: load transferred to dense layer or rock
  • Friction: load transferred through skin friction along shaft
  • Combination: most piles in practice

Soil bearing capacity (allowable)

Soil psf
Bedrock 8,000-25,000+
Dense sand 3,000-5,000
Medium sand 2,000-3,000
Stiff clay 2,000-4,000
Loose sand 1,500-3,000
Soft clay <1,500

Settlement

  • Immediate (granular): rapid
  • Consolidation (clays): slow, months to years
  • Total vs differential: differential more damaging
  • Typical max: 1" total, 1/2" differential for typical building

Frost depth (foundation minimum)

Region Depth
South Florida 0" (no frost)
Mid-Atlantic 24-30"
Midwest 36-42"
N New England 48-54"
N Minnesota 60"

Expansive vs collapsible soils

  • Expansive (clay): swells with water, shrinks dry — foundations heave
    • Mitigation: deep foundations bypassing zone, moisture control, structurally elevated slabs
  • Collapsible (silt, loess): collapses when wetted — settlement
    • Mitigation: pre-wetting/compaction, deep foundations

Lateral earth pressure

  • At-rest, active, passive pressures
  • Hydrostatic when below water table (drains critical)
  • Surcharge from adjacent loads
  • Designed by geotech + structural
  • Drainage essential to prevent buildup

Waterproofing

  • Membrane (sheet or fluid-applied)
  • Drainage board (protects membrane)
  • Perimeter drain (pipe in gravel to daylight or sump)
  • Sump pump for low water level
  • Vapor retarder on interior face

Foundation drainage

  • Footing drains: perimeter pipe in gravel
  • Slope to daylight or sump
  • Filter fabric to prevent clogging
  • Critical for basement spaces
12 Lateral Systems & Seismic Design

Lateral force-resisting systems

System R Notes
Special steel moment frame 8 High ductility, large drift
Intermediate steel moment frame 4.5 Moderate seismic regions
Ordinary steel moment frame 3.5 Low seismic regions
Special steel braced frame 6 High strength, less drift
Special concrete moment frame 8 High ductility, ductile detailing
Special concrete shear wall 6 Stiff, common
Ordinary masonry shear wall 2 Lower performance
Light-frame wood shear wall 6.5 Residential

Seismic base shear

V ≈ Cs × W

  • W = effective seismic weight
  • Cs = seismic response coefficient (per ASCE 7)
  • Heavier buildings = more seismic force
  • Lighter (steel, wood, mass timber) = less

Cs depends on

  • Spectral acceleration (site location, mapped values)
  • Site class (soil type — A rock to F poor)
  • Period (T) of building
  • R factor (system ductility)
  • Importance factor (Ie — Risk Category)

Risk Category & Ie

Category Use Ie
I Low risk (sheds, ag) 1.0
II Standard (most buildings) 1.0
III High occupancy / substantial hazard 1.25
IV Essential (hospitals, fire stations) 1.5

Drift limits

  • Typical 0.020 × story height (ordinary)
  • 0.015 × h for hospitals, schools (Risk III/IV)
  • 0.010 × h for some systems
  • Story drift check separate from strength check

Diaphragms

  • Rigid (concrete, well-attached steel deck): distributes load to walls by stiffness
  • Flexible (untopped metal deck, wood): distributes by tributary area
  • Semi-rigid: in between (most common, requires more analysis)

Soft story

A weak/soft level (often ground floor with parking or retail). Concentrates demand. Causes catastrophic collapse in earthquakes (Northridge 1994 examples). Need careful detailing or alternative configuration.

Wind vs seismic

Both lateral, but different characteristics:

  • Wind: steady + gust, predictable distribution, high-rises governed
  • Seismic: short-duration impulses, distributed per mass, low-rises often governed
  • Building designed for worst case at each story

P-delta effects

Secondary moments from gravity loads acting on laterally deflected building. Becomes significant in tall buildings and ductile systems. Code triggers analysis at stability ratio thresholds.

Hurricane / high-wind areas

  • HVHZ (High Velocity Hurricane Zone): Miami-Dade, Broward, parts of FL
  • Special impact-resistant glazing or shutters
  • Stricter component testing (ASTM E1996, E1886)
  • Roof to wall to foundation continuous load path
13 Live Loads by Occupancy (IBC Table 1607.1)

Typical uniform live loads (psf)

Light loads (≤ 60 psf)

Occupancy psf
Residential — 1-2 family 40
Residential — apartments/dorms 40-60
Hospitals — patient rooms 40
Hotels — guest rooms 40
Schools — classrooms 40
Offices 50
Roofs (typical) 20

Medium loads (60-100 psf)

Occupancy psf
Office corridors above first floor 80
Schools — corridors above first floor 80
Public corridors first floor 100
Stairs / exits 100
Assembly — fixed seating 60
Library — reading rooms 60
Stores — retail (1st floor) 100

Heavy loads (100-150+ psf)

Occupancy psf
Assembly — movable seating 100
Lobbies 100
Sidewalks, vehicular driveways 250
Garages — passenger 40
Garages — trucks varies
Library stacks 150
Manufacturing — light 75
Manufacturing — heavy 125
Storage — light 125
Storage — heavy 250

Roof live loads

  • Ordinary flat roof: 20 psf (reduces with tributary area)
  • Snow load: per ASCE 7 ground snow map + modifiers
  • Heavier roof live load required for green roofs (load varies)

Dead loads (DL) = weight of structure + permanent items. Live loads (LL) = occupants, furniture, snow, etc. Both factor into total design load.

14 Daylighting Design

Key metrics

DA (Daylight Autonomy)

  • % of occupied hours daylight alone provides target illuminance (typically 300 lux)
  • Target: DA300 ≥ 50% for primary occupied spaces

sDA (Spatial Daylight Autonomy)

  • % of floor area meeting DA threshold
  • LEED v4.1: sDA300/50% ≥ 55% for 1 point; ≥75% for 3 points

ASE (Annual Sunlight Exposure)

  • % of area exposed to direct sun >1000 lux for >250 hours/yr
  • Target: ASE1000,250 ≤ 10% to prevent glare/overheating

Daylight Factor (DF)

  • Static metric: indoor/outdoor illuminance ratio
  • DF >2% generally desirable

Strategies by orientation (N. Hemisphere)

North glazing

  • Even, diffuse light
  • No direct sun → no glare
  • Best for art galleries, design studios
  • Largest openings possible

South glazing

  • Brightest in winter (low sun)
  • Predictable shading with horizontal overhangs
  • Best controlled in passive solar design
  • Overhang depth: (winter solar altitude angle) determines

East/West glazing

  • HARDEST to control
  • Low sun angles → horizontal overhangs ineffective
  • Need vertical fins or external shades
  • Minimize glazing where possible (especially West)

Window-to-Wall Ratio (WWR)

  • Energy codes typically limit WWR to 30-40%
  • High WWR good for daylight but bad for heat loss/gain
  • Trade-off: glazing performance vs. quantity

Light shelves

  • Horizontal element above eye level
  • Reflects daylight onto ceiling, deeper into space
  • Effective for ~2× shelf height in penetration
  • Combine with proper overhang
15 Parking Design Rules of Thumb

Stall dimensions (typical)

Standard

  • 9' × 18' standard space
  • 8' × 18' compact (where allowed by code)
  • 10' × 20' large/luxury

Accessible

  • 8' × 18' space + 5' access aisle = car-accessible
  • 8' × 18' space + 8' access aisle = van-accessible
  • OR 11' × 18' + 5' aisle for van

Aisle widths (between rows)

Angle One-way aisle Two-way aisle
90° 24' (often) 24' (often)
75° 18' 26'
60° 16' 24'
45° 13' 22'

Required spaces (ADA)

Total spaces Required accessible Van-accessible
1–25 1 1
26–50 2 1
51–75 3 1
76–100 4 1
101–150 5 1
151–200 6 1
201–300 7 2
301–400 8 2
401–500 9 2
501–1000 2% of total 1 per 6 acc
Over 1000 20 + 1/100 1 per 6 acc

Garage clearances

  • Headroom: 7'-0\" min for standard; 8'-2\" for van-accessible
  • Drive aisle clearance: 14' typical for trucks/emergency
  • Sloped floor for drainage: ¼\"/ft minimum
  • Ramp slope: 6% max for vehicular; transitions at top/bottom

Sizing calculations

  • Surface lot: ~350-400 SF per car (incl aisle)
  • Single-floor garage: ~325 SF per car
  • Multi-level garage: ~300 SF per car (more efficient)
  • Underground garage: ~350 SF per car

Code minimums (zoning typically)

  • Office: 1 space per 200-400 SF
  • Retail: 1 per 250-300 SF
  • Restaurant: 1 per 100-150 SF (or per seat)
  • Residential: 1-2 per unit
  • Hotel: 1 per room + employees
16 Climate-Responsive Design

IECC Climate Zones (simplified)

Zone 1 — Very Hot (Miami, Honolulu)

  • Cooling-dominated
  • No heating typically required
  • High humidity (Zone 1A)
  • Strategies: shading, ventilation, reflective surfaces

Zone 2 — Hot (Houston, Phoenix)

  • Cooling-dominated
  • Hot humid (2A) or hot dry (2B)
  • Strategies: shading, thermal mass (dry only), light colors

Zone 3 — Warm (Atlanta, LA, Dallas)

  • Mixed cooling + some heating
  • Most complex shading optimization
  • Strategies: deep overhangs, cross-ventilation, modest insulation

Zone 4 — Mixed (Washington DC, Nashville)

  • Significant heating AND cooling
  • Hardest to optimize
  • Strategies: balanced insulation, smart vapor management

Zone 5 — Cool (Chicago, Boston, Denver)

  • Heating-dominated
  • Strategies: high insulation, vapor retarder interior, solar gain in winter

Zone 6 — Cold (Minneapolis, Anchorage south)

  • Strong heating dominance
  • Strategies: very high insulation, triple-glazing, wind protection

Zone 7-8 — Very Cold / Subarctic

  • Heating critical
  • Strategies: super-insulation, minimal glazing, vestibules

Vapor retarder placement

  • Zones 1-3: Exterior side (warm/humid outside)
  • Zone 4: Vapor-open assemblies preferred; no vapor retarder
  • Zones 5-8: Interior side (warm/humid inside)

Building orientation

  • Long axis E-W generally optimal in most climates
  • Maximizes north/south exposure (controllable)
  • Minimizes east/west (uncontrollable)

Glass selection (SHGC, Solar Heat Gain Coefficient)

Climate Recommended SHGC
Hot (1-2) 0.25 or lower
Mixed (3-4) 0.25-0.40
Cold (5-8) 0.40-0.55 (capture winter sun)

U-factor (heat transmission) and SHGC (solar gain) are both critical and don't always track together. Low-e coatings tune both.

17 Structural Rules of Thumb

Beam depth (preliminary)

Material Depth ratio
Steel W-shape Span / 20
Steel joist Span / 24
Concrete beam Span / 12-15
Concrete one-way slab Span / 24-28
Concrete two-way slab Span / 30-33
Post-tensioned slab Span / 35-45
Wood joist Span / 15-18

Typical span ranges

System Span (ft)
Wood joists 12-22
Light-gauge steel 18-26
Steel beam + deck 30-50
Steel girder + beam 50-80
OWSJ (K) 30-60
OWSJ (LH/DLH) 60-240
Concrete flat slab 25-30
Concrete waffle 30-60
Concrete PT 30-40

Lateral systems

  • Moment frame: Open plan, less efficient
  • Braced frame: Efficient, blocks bays
  • Shear wall: Very efficient, blocks entirely
  • Dual system: Moment + braced/shear

Foundations

Type When
Spread footing Good soil, columns
Strip footing Bearing walls
Mat (raft) Weak soil, full coverage
Driven pile Deep bearing layer
Caisson Heavy load, deep
Helical pier Small load, low disturbance

Footings must extend below frost depth — varies 0-72" by climate zone.

18 Envelope Systems

Four control layers (priority order)

  1. Water (bulk water) — sheds liquid
  2. Air — must be CONTINUOUS
  3. Vapor — warm side of insulation
  4. Thermal — continuous, avoid bridging

Rain screen principle

Cladding + air cavity + air/vapor barrier (inboard)

  • Cladding sheds most water
  • Cavity drains incidental water
  • Air/vapor barrier handles the rest
  • Decouples water from air/vapor management

Vapor retarder placement

Climate Side
Cold (zones 5-8) Interior
Hot/humid (1A-2A) Exterior
Mixed (zone 4) Vapor-open or smart

Curtain wall systems

System Use Height
Storefront 1-2 story ≤20 ft
Window wall Floor-supported Mid-rise
Stick curtain wall Slab-bypass, on-site Mid-rise+
Unitized curtain wall Pre-fab panels Mid-rise+

Thermal bridging mitigation

  • Continuous exterior insulation (best)
  • Thermal breaks at slab edges, balconies
  • Steel stud cavities: continuous insul. on top
  • Aluminum framing: thermally broken

Thermal bridges can reduce effective R-value 40%+. Spec continuous exterior insulation for high performance.

19 MEP Sizing

Cooling loads (rule of thumb)

Building type Tons per SF
Office (efficient) 1 / 400-500
Office (older) 1 / 250-350
Retail 1 / 200-300
Restaurant 1 / 100-200
Lab/medical 1 / 150-250
Residential 1 / 400-600

1 ton = 12,000 BTU/hr

Duct velocities (commercial)

Run Velocity (fpm)
Main supply 1500-2500
Branch supply 700-1200
Return 500-1000
Exhaust 1500-2500

Sizing: A (sf) = Q (cfm) / V (fpm)

Electrical loads

Building type W/SF
Office 6-8
Retail 8-10
Restaurant 15-25
Lab 25-50
Data center 100-300

Plumbing (Fixture Units)

Fixture DFU
Lavatory 1
WC (tank) 3-4
WC (flush valve) 6-8
Shower 2
Floor drain 2
Kitchen sink 2

HVAC system types

  • VAV — variable air volume, constant temp
  • CAV — constant air, variable temp
  • DOAS — dedicated outdoor air system
  • Chilled beam — radiant cooling + DOAS
  • VRF — variable refrigerant flow
20 Egress Detailed

Three components

  1. Exit Access — any point → exit
  2. Exit — protected (stair enclosure, passageway, exterior door at grade)
  3. Exit Discharge — exit → public way

Door swing

Swing in direction of egress when:

  • Occupant load 50+
  • Group H (any load)
  • Horizontal exit
  • Exit discharge (most cases)

Exit width sizing

Required width = Occupants × Factor

  • Level egress (corridor, door): 0.2 in/occupant
  • Stairs: 0.3 in/occupant
  • Sprinklers reduce by ~80% (already in factors)

Minimum widths (most occupancies)

Element Min Width
Corridor 44"
Door 32" clear
Stairs 44"
Aisle (Assembly w/ seats) 36-66"

Travel distance (sprinklered)

Group Max travel
A, E, F-1, M, R, S-1 250 ft
B, F-2, S-2, U 300 ft
H-1 75 ft
H-2 100 ft
H-3 150 ft
H-4 175 ft
I-1, I-2, I-3 250 ft

Common path of travel (sprinklered)

Group Max common path
Most (low occupant load) 75-125 ft
H 25-75 ft

Dead-end corridor (sprinklered)

Group Max
B, F, S, U 50 ft
Most others 20 ft

Two exits required when:

  • Occupant load >49 (most)
  • Common path exceeded
  • Travel distance to single exit exceeded
  • Some occupancies require sooner (H, I)

Three or more exits

  • 3 exits: 501-1000 occupants
  • 4 exits: >1000 occupants
21 Accessibility (ADA / ANSI A117.1)

Reach ranges

Reach Max Min
Forward, unobstructed 48" 15"
Side, unobstructed 48" 15"
Forward, obstructed 44"
Side, obstructed 46"

Maneuvering clearances

  • Turning space: 60" circle OR T-shape
  • Pull-side door: 60" deep × 18" beyond latch
  • Push-side door: 48" deep × 12" beyond latch (if closer + latch)
  • Knee clearance: 27" h, 30" w, 11" deep
  • Toe clearance: 9" h, 6" deep

Routes & ramps

  • Running slope <1:20 (5%) = accessible walking surface
  • >1:20 = RAMP (max 1:12 / 8.33%)
  • Max ramp rise: 30" per run
  • Cross slope: 1:48 (2.08%) max anywhere
  • Min width: 36" (48" preferred)

Stairs (accessible egress)

  • Tread: 11" min
  • Riser: 4" min, 7" max
  • Uniform throughout flight
  • Closed risers (no open backs)
  • Handrails: 34-38" both sides
  • Handrail extensions: 12" top, 1 tread depth bottom

Toilets

  • Accessible stall: 60" w × 56" d (wall-hung)
  • WC centerline: 16-18" from wall
  • Seat height: 17-19"
  • Grab bars: rear 36" min, side 42" min
  • Flush controls: open side
  • Door: out-swing or large stall

Parking

Total spaces Accessible Van
1-25 1 1
26-50 2 1
51-75 3 1
76-100 4 1
101-150 5 1
151-200 6 1
201-300 7 2
301-400 8 2
401-500 9 2
501-1000 2% of total 1 per 6 accessible

1 of every 6 accessible spaces must be van-accessible (rounded up).

22 Structure

Lateral systems

  • Moment frame — rigid joints; open plan; less efficient
  • Braced frame — diagonals; efficient; obstructs openings
  • Shear wall — solid wall; very efficient; blocks openings
  • Dual system — moment + braced/shear

Loads

  • Dead — permanent (structure, finishes, MEP)
  • Live — variable (occupants, furniture)
  • Wind — lateral pressure; location, height, exposure
  • Seismic — ground acceleration; zone + site class
  • Snow — ground snow load + roof factors

Typical bay sizes

  • Wood: 16-20 ft
  • Light steel: 18-22 ft
  • Steel deck/concrete: 30-40 ft
  • Concrete flat slab: 25-30 ft
  • Long-span: 60-120 ft
23 Envelope

Four control layers

  1. Water (bulk water) barrier
  2. Air barrier — must be continuous
  3. Vapor retarder — warm side of insulation
  4. Thermal barrier — continuous to avoid bridging

Rain screen

Cladding + air cavity behind. Cladding sheds most water; air barrier (inside cavity) controls air/vapor. Decouples water management from air/vapor.

Place vapor retarder on warm side. Cold climates: interior. Hot/humid climates: exterior.

Thermal bridging

Conductive paths (steel studs, slab edges, balconies) bypass insulation — can drop effective R-value 40%+. Mitigate with continuous exterior insulation.

24 Egress

Three components

  1. Exit Access — any point to an exit
  2. Exit — protected (enclosed stair, exit passageway, exterior door)
  3. Exit Discharge — from exit to public way

Key distances (sprinklered)

  • Common path — typ. 75–100 ft
  • Dead-end corridor — typ. 20–50 ft
  • Travel distance — typ. 200–300 ft

Egress width

Occupant load × factor:

  • Level egress (corridors, doors): 0.2 in/occupant
  • Stairs: 0.3 in/occupant

When 2 exits required

  • Most occupancies: occupant load >49 OR common path exceeded
  • 3 exits: 501-1000 occupants
  • 4 exits: >1000 occupants
25 Accessibility

Slope thresholds

  • <1:20 (5%): Accessible walking surface
  • >1:20: Ramp territory
  • Max 1:12 (8.33%) running slope for ramps
  • Max 30\" rise per ramp run before landing

Clearances

  • Turning radius: 60\" diameter circle
  • Knee clearance: 27\" h × 11\" deep
  • Toe clearance: 9\" h × 6\" deep

Accessible parking

  • 1-25 spaces: 1 accessible
  • 26-50: 2 / 51-75: 3 / 76-100: 4
  • 1 of every 6 accessible must be van-accessible

Study PPD the way it's tested

Reading is the start. An account adds 140 spaced-repetition flashcards, 110 practice questions, and 3 timed mock exams for PPD — plus the other five divisions, synced across web, iOS, and Android.

Start your 7-day free trial

The other five divisions

Every plan includes all six. Study them in any order.